Please see below the numbers for Dzembo’s project.

As you can see
inon the sheet below, our projected profit was 40%. However, due to unplanned additional expenses, we are at negative at $ 1,191.40 on what we had budgeted to cover the costs for this project.

So, as of today our profit is at $6,818.15 or 34%, a loss of 6% of profit.

Is there any way we can save money? Maybe we can negotiate the price of the cabinets install? I’m calculating $
3,097 for install, resulting in a profit of 34%. If we can reduce this expense, that would be great.

*** Last Bills To Be Paid (Projected Amounts)

- Installation of cabinets: $
3,097
- Deco Hardware Installation: $
300
- Cleaning Services: $
100

*** Where we
have spent more than we projected

- Cabinets: $
1,373.75 more

- Plumbing Fixtures: $
24.94 more

TOTAL: $
1,398.69

(Other items offset the loss, leaving it at $
1,191.40)

The text above was approved for publishing by the original author.

Previous       Next

נסו בחינם

אנא הכנס את הודעתך
אנא בחר באיזו שפה לבצע את התיקון

לחצו כאן אם אתם צריכים לעשות הגהה לקורות החיים שלך.

eAngel.me

eAngel.me is a human proofreading service that enables you to correct your texts by live professionals in minutes.