You can raise an NCR against it,; will remove the rods. WeWe are trying to work with BB, trying to bring some dates forward from your program 11.5, hence that's why we are on level 1-3 fitting FCU, which we are not meant to start till 31/05/2022.
Please see the attachment for the M&E package for block E. We are in the process to handof handing the new program for Block E, also for the rest of the blocks this week. If we go by your program, we are not to start any work till 25/04/2022 any works.
As for the delivery that was scheduled today, I'll let you know at 8:30am what comecame in. Can you let me know when Prates wouldwill have theretheir roof workswork completed so we can penetrate with our ductwork?
The RWP connections needs to be confirmed by yourselfyou when we can penetrate to the roof, which you have not confirmed. You haven't confirmed ifwhether the holes are broken out.
The text above was approved for publishing by the original author.
Previous
     
Next
פשוט גש לתיבת האימייל שלך, ולחץ על הלינק לאימות, ומייד נתקן עבורך את האיימייל. אם אתה רוצה לתקן עוד אימיילים אז:
או